a contactor hired 150 men to pave a road in 30 days.how many mem will be hire to do the same work in 20 days​

Respuesta :

kevinmario2008 kevinmario2008
  • 05-12-2021

Answer:375

Step-by-step explanation:W = RTN

1 = 1/7500(20)N

1 = 20/7500N

1 = 2/750N

750(1 = 2/750N)

750 = 2N

750/2 = N

375 = N

There are 375 men to do the job in 20 days

Answer Link

Otras preguntas

The sum of two numbers is 9. If one number is subtracted from the other, the result is 5. Find the numbers.
What is one possible reason that the Romans overthrew the Etruscans in 509 B.C.E.?
How do you find the circumference of a circle? Show two different formulas.
What circumstances does Kevin experience that show he is probably not growing up in the contemporary United States?
A grain silo has a diameter of 4.4 meters. The height of its cylindrical portion is 6.2 meters.
Correct answer gets brainliest and full ratings.
Intuition often leads us to believe that extroverted people who can speak coherently about their goals and their jobs are more likely to perform well. which bia
What is an example of arithmetic programming expression?
College students are offered a 8​% discount on a textbook that sells for ​$ 45.50. If the sales tax is 8​%, find the cost of the textbook including the sales ta
which alliance enjoyed the best geological position in WW1