What element of a timeline helps to mark progress of the project?
O A. milestones
O B. job responsibilities
O C. external deliverables
OD. internal tasks

Respuesta :

Kekebad578
Kekebad578 Kekebad578
  • 02-04-2020
The answer is A.milestones
Answer Link

Otras preguntas

Which substance can be decomposed by chemical means? (1) tungsten (3) krypton (2) antimony (4) methane
Domestically, President Nixon was most concerned with increasing civil rights strengthening federal power restoring law and order aiding military power
Which sample contains particles in a rigid, fixed, geometric pattern?(1) CO2(aq) (3) H2O(ℓ)(2) HCl(g) (4) KCl(s)
What is HDI? What factors influence the HDI of a country the most?
What is the slope of the line with equation y = –3? I have no idea how to do this.
The modern model of the atom is based on the work of(1) one scientist over a short period of time(2) one scientist over a long period of time(3) many scientists
how was the idea of citizenship changed throughtout histpry
1.the current atomic model would be revised if? A.)better microscopes were being used to study its structure B.) better microscopes are invented in the future
Solve by using the perfect squares method. x2 + 16x + 64= 0 a. –8 b. –16 c. 8 d. 16
An Arrhenius acid has (1) only hydroxide ions in solution (2) only hydrogen ions in solution (3) hydrogen ions as the only positive ions in solution (4) hydroge