A critical activity is________________.a. an activity that consumes no time but shows precedence between events. b. a milestone accomplishment within the project. c. an activity with zero slack. d/ the beginning of an event.

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 09-03-2020

Answer:

C

Explanation:

Critical activity is the sequential activities from beginning to the end of a project. A lot of projects have a single critical path, although some projects may have more than one critical activity which depends on the flow logic utilized in the project.

Answer Link

Otras preguntas

Haley needs to rent a moving van for the day. Company A charges $75 plus $0.25 per mile. Company B charges $50 plus $0.75 per mile. For how many miles is compan
Please answer the picture below.
Lee y escribe un diálogo. Read and write a dialogue. Escribe un diálogo corto en español entre un amigo o amiga y tú en oraciones completas. Usa las palabras de
1. Mr. Li did some push-ups on Monday and Tuesday. On Tuesday, he did 300 push-ups, which was three times the difference of the number of push-ups he did on Mo
Why was Jefferson accused of being an atheist and what does that reveal about politics and culture of the time
which statement about the graph of a horizontal line is true?​
1. Name the two major divisions of the nervous system.
Fill in the blank so that the following equation has one solution __x+4=2x+__ A. 4,3 B.2,5 C. 2,4
can override the brain's other functions. A. Emotions B. Smells C. Music D. Calmness
What is the maximum amount of cholesterol a "healthy" snack can contain, according to the FDA? A. 3 mg B. 30 mg C. 60 mg D. 80 mg